The Project

As part of the planned work, the existing asphalt roadway will be rehabilitated to improve ride quality and skid residence.

The Scope of Work

To be determined.

What This Means to You

We will have a better idea of the timeline once the design is finalized and a contractor is selected.

Project Updates

The road work began on September 24, 2025 with shoulder widening and ditch cuts.

Construction will start at the north end of Range Road 230 and work south to Township Road 560 then toward Hwy 28A.

The road will remain open to traffic; with one lane closed at times. Please obey all signs and flagman directions when travelling through the area.

Construction began on September 19, 2025, with brushing and fence removal.

The main roadwork is scheduled to start on September 24, 2025, beginning at the north end of Range Road 230 and moving south to Township Road 560, then toward Hwy 28A. Work will include shoulder widening and ditch improvements.

The road will remain open during construction; however, there may be times when traffic is reduced to one lane. Please watch for signs and follow the directions of flaggers for everyone’s safety.

Construction will begin mid September 2025.

The project is scheduled to begin in early September.

Construction is scheduled to begin early in September.

Construction is now scheduled to begin in early September.

Construction to begin end of August.

Construction is scheduled for mid-August.

Construction is scheduled to begin in mid-August.

Construction is scheduled to begin in mid-August.

Construction is scheduled to begin in mid-August.

Construction is scheduled to begin mid-August.

A start date has not been confirmed, but we will share updates here as soon as more information is available.

A start date has not been confirmed, but we will share updates here as soon as more information is available.

A start date has not been confirmed, but we will share updates here as soon as more information is available.

Crews are now trimming and clearing brush along the side of the road. This is necessary to prepare for the upcoming construction season.