The Project

The project will rehabilitate the roads within Surgeon Valley Estates.

Project Scope

Subdivision rehabilitation and Range Road 230 asphalt overlay.

What This Means to You

Residents can expect minor traffic disruptions. The project is expected to wrap up by the end of August 2025.

Project Updates

Landscaping is underway.

Landscaping around the project area is now underway.

Landscaping around the project area is now underway.

Landscaping will start after the paving is finished.

Landscaping will start after all the paving is finished.

The paving is underway, landscaping will start once all the paving is done.

The gravel work is 95 per cent done. Paving is underway and it is expected to be done by July 11, weather permitting.

Paving is expected to begin the week of June 23rd, if the weather allows.

Construction work continues. Please use caution and follow posted signage when travelling near the work zone.

Culvert replacement work is underway—drivers should expect delays in the area. Asphalt pulverization was scheduled for the end of May.

Weekly updates on this project will be added to this section.