The Project

The existing bridge culvert will be replaced with a new corrugated steel pipe (CSP) culvert. Construction is expected to be done by October 15, 2023. (BF 75343)

The Scope of Work

  • Various permitting agreements and approvals for the new bridge structure.
  • Excavation of the road and removal of the existing culvert.
  • Assembly and installation of the new CSP culvert.
  • Rebuilding Rge. Rd. 263 within the project limits.

What This Means to You

Traffic along Rge. Rd. 263 could be temporarily reduced to one lane while the culvert is installed.

Project Updates

The design work is underway and tender preparations are being worked on.