The Project

This project will repair and stabilize the slope adjacent to the walking trail in Pinnacle Ridge. It is anticipated that the project will be done by the end of June.

The Scope of Work

To repair and stabilize a slope allowing continued use of the path.

What This Means to You

The gravel trail is now closed until the construction is done.



Project Updates

The project is almost finished; a fence needs to be put up, and seeding is required.

Construction crews are paving the trail today, June 12. The trail should be open for use tomorrow, June 13.

Crews still have minor landscaping to do along with putting in a fence.

Construction done in the previous week includes:

  • slope repair is done,
  • surface drainage earthwork is done, and
  • final grading and landscaping is in progress.

The remaining work includes erosion control blanket and hydro seeding, trail paving, and fence installation.

Construction on the project continues as scheduled.

Work started again today. The end of June is still the anticipated completion date.

It is expected that the project will be 90% done in 2022. The remaining landscaping and trail paving will happen in 2023.

Construction is in progress.

Design work for this project is underway.