The Project
The current alignment of Carbondale Road is outside of the proper right-of-way. The correct alignment is about 20 metres northeast of its current location. Moving the road to the correct right-of-way will also allow for drainage control and future erosion. Weather permitting, the project should take about two months to complete.
The Scope of Work
- The reconstruction of about 750 metres of roadway.
- The removal and replacement of centreline culverts.
- Roadside ditching and erosion control issues.
- Regrading of the area where the current alignment exists.
What This Means to You
Construction will involve slow moving equipment and noise during daytime working hours.
As much as possible, there will be continuous access for traffic managed by construction crews. There is the potential for a brief road closure.
Re-oiling will take place in phases with advance resident notification.
Project Updates
Due to weather conditions, the start of the Carbondale Road realignment project is delayed until September. (Red project area on the map to the right.)
The drainage improvements are done, and the road rehabilitation work is about 90 per cent complete. (Yellow project area on the map to the right.)
Phase 1 oiling is done, the road will reopen as planned. The guardrail will be added on July 5.
Project page created.