The Project
The pedestrian bridge in the Casa Vista subdivision has been in service since the 1980s. It is in poor condition and needs major repairs, and it is currently closed for use. The County is planning a major rehabilitation of the structure in the upcoming construction season.
Project Scope
During the initial bridge assessment in 2023, the plan was to rehabilitate the existing structure. This would involve rehabilitating the existing bridge structure and replacing the bridge’s supporting components.
In June 2024, based on further site investigations and the results of the project tender process, the County is exploring other more cost-effective options.
In 2025, the existing pedestrian bridge will be rehabilitated, replaced, or removed.
What This Means to You
The bridge is closed and not safe for use.
Project Updates
The County is currently pursuing a design-build rehabilitation option for the bridge. More information on how the project will move forward will be available in early October 2025.
The County continues to advance a design-build rehabilitation option for the bridge. An update on next steps and project direction will be shared in early October 2025.
The County is currently pursuing a design-build rehabilitation option for the bridge.
More information on how the project will move forward will be available in early October 2025.
The project is currently on hold as the County and the previously selected contractor were unable to reach a final agreement.
The County is exploring alternative options to complete the project. As a result, the construction timeline is currently uncertain, but work is anticipated to begin in early 2026.
The project is currently on hold as the County and the previously selected contractor were unable to reach a final agreement.
The County is exploring alternative options to complete the project. As a result, the construction timeline is currently uncertain, but work is anticipated to begin in early 2026.
It is anticipated the project will commence in late August and proceed until late October / November 2025.
An updated schedule from the contractor is expected in the next few weeks. It is anticipated that the project will begin in late August and wrap up late October/November 2025.
An updated schedule from the contractor is expected in the next few weeks. It is anticipated that the project will begin in late August and wrap up late October/November 2025.
It is expected that the project will begin in late August and wrap up in late October or November 2025.
It is expected that the project will begin in late August and wrap up in late October or November 2025.
The project is still expected to begin around mid-July and finish late October 2025.
The project is still expected to begin around mid-July and finish late October 2025.
The project is still expected to begin around mid-July and finish late October 2025.
It is expected that the work will begin around mid-July and be completed by late October 2025.
It is expected that the work will begin around mid-July and be completed by late October 2025.
Join us on June 11 to learn more about this project and others in your area.
Wed. June 11 at 7 PM
Gibbons Community Cultural Centre, Pembina Room
Construction on this project has not yet begun. More information, including timelines, will be shared soon.
In June 2024, based on further site investigations and the results of the project tender process, the County is exploring other more cost-effective options.
Construction is delayed until further notice.
The bridge remains closed and is not safe for use.
Information about this project will be posted on this project page.