The Project

In 2025, Sturgeon County will rehabilitate Lamoureux Drive from Highway 15 to Range Road 224A.

Project Scope

There is a proposed realignment of Lamoureux Drive, which is intended to create a safer separation between the road and the multi-use trail.

What This Means to You

Sturgeon County will advise residents if any temporary road closures are necessary.

Project Updates

This project is now done.

Paving, topsoil placement, and seeding are complete. Remaining signage and cleanup are scheduled to be finished by September 25.

Ditch cleanup and topsoil placement are ongoing. The final lift of pavement is scheduled for September 11 to 13, with all remaining work expected to be completed by late next week.

Construction resumed after a brief break by the contractor.

Grading and gravel work is now done. The remaining bottom layer of asphalt work was scheduled for August 28 and 29. Ditch clean up, topsoil placement, and seeding work is ongoing.

The contractor plans to shut down from August 30 to September 1. Construction will resume on September 2.

Crews are continuing grading and gravel work toward the west end of the project. On the east side, the first layer of asphalt has been finished for about 1 kilometre.

Grading and culvert work continues. The east section of the project is almost done with gravel and pavement scheduled for early August. The contractor continues with grading work working west.

Grading and culvert work continues. The east section of the project is almost done with gravel and pavement scheduled for early August. The contractor continues with grading work working west.

The project is in progress.

Grading work continues on this project.

Grading work continues on this project.

Grading for the project is still scheduled to begin the week of July 7.

The construction crew will begin moving equipment to the site on July 3. Site preparations will start that week with grading scheduled for the week of July 7.

The contractor is still on track to start in late June 2025.

The contractor is still on track to start in mid to late June 2025.

It is anticipated that construction will begin mid to late June.

Weekly updates on this project will be posted in this section.